Completing the Exterior
Last Updated 11 January 2003
October 29. Roof framing is proceding.
.November 9.
.
November 28. Roof sheathing continues..
December 13. Roofing felt is down. Now that we're watertight, let it rain!
.
January 2. A nice day early in the new year..
Janary 15. Install windows and begin the stucco lath..
January 16..
January 22. Throw on the roof shingles..
January 25..
January 28. Four inches of snow is unusual, but somewhat attractive..
February 4. Trim painting has begun. Stucco on the exterior and sheet rock on the interior will commence.
To Be Continued!